Lesson 3D.4.3

3D.4.3 Critical path algorithm Quiz: Pearson Edexcel Further Maths, Unit 38

20 questions

In partnership with Revision Ninja

Lesson 3D.4.3, Critical path algorithm: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. Critical activities are those with

    • no predecessors
    • maximum total float
    • zero total float
    • the longest duration
  2. The forward pass in the critical path algorithm computes

    • earliest event times
    • resource levels
    • latest event times
    • total float of each activity
  3. The backward pass computes

    • earliest event times
    • earliest start times of activities only
    • critical durations
    • latest event times
  4. The critical path is

    • a shortest path from start to finish
    • a longest path from start to finish made of critical activities
    • a path whose activities all have positive float
    • the path with the most activities regardless of duration
  5. The earliest time for an event is found by taking

    • the average of the incoming durations
    • the minimum over incoming activities of the same sum
    • the sum of all incoming durations
    • the maximum over incoming activities of the earliest start of the tail plus the duration
  6. The latest time for an event is found by taking

    • the sum of all outgoing durations
    • the minimum over outgoing activities of the latest time at their head minus the duration
    • the maximum over outgoing activities of the same difference
    • the earliest time plus the duration
  7. The project duration is equal to

    • the earliest time at the finish event
    • the latest time at the start event
    • the longest single activity duration
    • the sum of all activity durations
  8. Start node 0 has earliest time 0. Activity 0-1 takes 3, 0-2 takes 5, 1-3 takes 4, 2-3 takes 1 and 3-4 takes 6. What is the project duration?

    • 7
    • 13
    • 18
    • 12
  9. In the same network, the latest time at node 3 is 7. What is the latest time at node 2, where the activity 2-3 takes 1?

    • 6
    • 8
    • 7
    • 5
  10. In the same network (durations 0-1: 3, 0-2: 5, 1-3: 4, 2-3: 1, 3-4: 6), which activities form the critical path?

    • 0-1, 2-3 and 3-4
    • 0-1, 1-3 and 3-4
    • 0-2 and 2-3 only
    • 0-2, 2-3 and 3-4
  11. In the same network, what is the total float of activity 0-2, which takes 5, given earliest time 0 at node 0 and latest time 6 at node 2?

    • 1
    • 0
    • 5
    • 6
  12. An event has earliest time 4 and latest time 4. What can be said about it?

    • it is critical, with zero float
    • it cannot be reached
    • it has a float of 4
    • it is not critical
  13. An activity has earliest start 2, duration 4 and its head event has latest time 9. What is its total float?

    • 5
    • 1
    • 3
    • 0
  14. An event has two incoming activities: one from node 0 (earliest time 0, duration 4) and one from node 1 (earliest time 2, duration 7). What is the earliest time at this event?

    • 4
    • 9
    • 6
    • 11
  15. A node has outgoing activities to node 5 (duration 3, latest time 12) and to node 6 (duration 4, latest time 10). What is the latest time at this node?

    • 9
    • 6
    • 12
    • 7
  16. How many critical paths can a network have?

    • one or more
    • none
    • exactly two
    • exactly one
  17. Why does an activity with zero total float have to be critical?

    • it always has the longest duration
    • its earliest and latest times are always different
    • it has no predecessors
    • any delay to it delays the whole project, so it lies on a longest path
  18. An activity runs from node 2 to node 3 and takes 4. Node 2 has earliest time 8, and node 3 has latest time 12. What is the total float of this activity?

    • 4
    • 1
    • 2
    • 0
  19. Why compute latest times by working backwards from the finish?

    • because the forward pass is impossible
    • to find the latest each event can occur without delaying completion
    • to count the number of activities
    • to find the cheapest route through the network
  20. A network has edges 0-1 (2), 0-2 (6), 1-3 (5), 2-3 (1), 3-4 (4) and 1-2 (3). What is the project duration?

    • 11
    • 7
    • 12
    • 9

All Pearson Edexcel Further Maths quizzes