Lesson 3D.4.4

3D.4.4 Total float and Gantt charts Quiz: Pearson Edexcel Further Maths, Unit 38

20 questions

In partnership with Revision Ninja

Lesson 3D.4.4, Total float and Gantt charts: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. Total float F(i,j) of an activity (i,j) is defined as

    • e_j - l_i + duration(i,j)
    • e_i - l_j - duration(i,j)
    • l_j - e_i - duration(i,j)
    • l_j - e_j - duration(i,j)
  2. Total float of an activity is

    • the time between its start and finish only
    • the amount it can be delayed without delaying project completion
    • the time its workers spend idle
    • the sum of the floats along the whole path
  3. A Gantt chart shows

    • the workers' pay for each activity
    • the net profit of the project
    • each activity as a bar on a time axis, with its start and duration
    • only the precedence table
  4. On a cascade Gantt chart, an activity with total float is drawn

    • as a single point at its latest finish
    • as a bar starting at its latest start only
    • only if it is on the critical path
    • as its earliest-start bar, with a line showing the float after it
  5. A cascade chart is another name for a

    • Venn diagram
    • histogram
    • precedence table
    • Gantt chart
  6. The earliest start of activity (i,j) is

    • e_j, the earliest time of event j
    • l_i, the latest time of event i
    • e_i, the earliest time of event i
    • l_j, the latest time of event j
  7. The latest finish of activity (i,j) is

    • e_j, the earliest time of event j
    • l_i + duration(i,j)
    • l_j, the latest time of event j
    • e_i, the earliest time of event i
  8. An activity has earliest start e_i = 4, latest finish l_j = 12 and duration 5. What is its total float?

    • 5
    • 12
    • 3
    • 8
  9. An activity has earliest start e_i = 0, latest finish l_j = 6 and duration 6. What is its total float?

    • 12
    • 0
    • 6
    • -6
  10. An activity has e_i = 2, l_j = 7 and duration 3. What is its total float?

    • 7
    • 2
    • 4
    • -2
  11. An activity starts at its earliest time 3, lasts 4 and has total float 2. What is its latest finish?

    • 11
    • 7
    • 5
    • 9
  12. An activity has total float 5 and lasts 3 days. It is delayed by 4 days. What happens to the project completion?

    • No change
    • Project delayed by 4
    • Project delayed by 9
    • Project delayed by 1
  13. An activity has earliest start 5, duration 3 and total float 4. What is its latest start?

    • 8
    • 12
    • 7
    • 9
  14. An activity has e_i = 8, l_i = 10, duration 3, e_j = 11 and l_j = 12. What is its total float?

    • 0
    • 3
    • 1
    • 4
  15. An activity Y starts at its earliest time 4, lasts 10 and has total float 6. What is its latest finish?

    • 16
    • 20
    • 24
    • 14
  16. Why can total float be shared between activities on the same path?

    • a delay on one float-carrying activity uses up float shared with later activities on that path
    • floats are only defined for critical paths
    • each activity has private float only
    • floats always add up
  17. An activity has duration 6, earliest start 2, and its head event has latest time 9. What is its latest start?

    • 9
    • 2
    • 3
    • 1
  18. Activities A (time 0 to 3), B (time 1 to 5) and C (time 3 to 6) are drawn on a Gantt chart. How many are active at time 2?

    • 3
    • 1
    • 0
    • 2
  19. Why does delaying a critical activity delay the project, while delaying within its float does not?

    • a critical activity has no float, so any delay pushes the finish back, whereas a delay within float only uses slack
    • critical activities have longer durations than others
    • float is always shared between all activities
    • delays only matter when workers are idle
  20. An activity has earliest start 3, duration 4 and latest head event time 10. What is its total float, and is it critical?

    • 3 units, not critical
    • 3 units, critical
    • 0 units, critical
    • 7 units, not critical