Lesson 3D.4.5-3D.4.6
3D.4.5-3D.4.6 Resource histograms and scheduling with workers Quiz: Pearson Edexcel Further Maths, Unit 38
20 questions
In partnership with Revision Ninja
Lesson 3D.4.5-3D.4.6, Resource histograms and scheduling with workers: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.
Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.
The 20 questions
-
A resource histogram plots
- cost against activity
- event times against event number
- the number of workers needed against time
- float against duration
-
Resource levelling aims to
- shorten the project below its critical path length
- smooth the number of workers needed over time, by using floats
- maximise the number of workers at any time
- remove the dummy activities
-
A lower bound on the number of workers needed to finish in time T is
- T multiplied by the number of activities
- the number of activities divided by T
- the largest number of workers on any one activity
- total worker-time divided by T, rounded up
-
In the scheduling problems here, the number of workers needed for each activity
- is always exactly one
- is always zero
- is chosen freely by the planner
- is given and may be more than one
-
The height of a resource histogram at a given time shows
- the total number of workers working at that time
- the cost of the workers
- the duration of the project
- the float of the critical path
-
Delaying non-critical activities within their float can
- increase the peak number of workers
- remove activities from the critical path
- reduce the peak number of workers needed
- always shorten the project
-
The minimum project duration when workers are unlimited is
- the sum of all activity durations
- the largest total float
- the total worker-time
- the length of the critical path
-
Activity X runs from time 0 to 4 with 2 workers. Activity Y runs from time 1 to 3 with 1 worker. How many workers are needed at time 2?
- 2
- 4
- 1
- 3
-
Activities A (3 days, 2 workers), B (4 days, 1 worker) and C (2 days, 3 workers) are in a project. What is the total worker-days?
- 16
- 24
- 12
- 9
-
A project needs 30 worker-days and must finish in 6 days. What is the lower bound on the number of workers?
- 5
- 3
- 6
- 30
-
An activity uses 3 workers for 2 days and has 3 days of float. What is its worker-time?
- 6
- 5
- 9
- 3
-
The project has capacity for 4 workers. Two activities need 3 and 2 workers at the same time. What must happen?
- more workers are hired automatically
- one must be delayed, within its float, so they do not overlap
- the project duration must shorten
- both can run since 5 is close to 4
-
Days 1 and 2 use 3 workers each day, and days 3 to 5 use 1 worker each day. What is the total worker-days?
- 9
- 11
- 12
- 6
-
A project has total worker-time 20 and must finish in 7 days. What is the minimum number of workers?
- 7
- 2
- 3
- 20
-
Daily worker numbers over five days are 2, 4, 3, 5 and 1. What is the peak number of workers?
- 15
- 4
- 3
- 5
-
A project has total worker-time 26 and must finish in 5 days. What is the minimum number of workers?
- 6
- 26
- 5.2
- 5
-
Two activities each need 2 workers for 3 days. One may start up to 3 days later without delaying the project. What is the lowest achievable peak?
- 6
- 3
- 2
- 4
-
Why can the minimum number of workers exceed the worker-time lower bound?
- the lower bound is always wrong
- work cannot always be split evenly over time because of precedence and fixed activity durations
- each activity needs exactly one worker
- histograms count dummy activities
-
Why can scheduling with the fewest workers lengthen the project?
- delaying activities to share workers can push critical activities back and extend the finish
- workers cannot be reassigned between activities
- the critical path is ignored when workers are shared
- fewer workers always lower costs
-
Daily peaks of workers over five days are 3, 5, 2, 6 and 1. What is the maximum number of workers needed?
- 17
- 5
- 3
- 6
Related quizzes
- Activity networks and precedence tables Quiz · 3D.4.1-3D.4.2 · 20 questions
- Critical path algorithm Quiz · 3D.4.3 · 20 questions
- Total float and Gantt charts Quiz · 3D.4.4 · 20 questions
- Proof by mathematical induction Quiz · 1.1 · 20 questions
- Quadratic equations and complex arithmetic Quiz · 2.1-2.2 · 20 questions
- Matrix arithmetic and inverses Quiz · 3.1-3.2 · 20 questions
- Expectation of discrete random variables Quiz · 3B.1.1 · 20 questions
- The Poisson distribution Quiz · 3B.2.1 · 20 questions
- Geometric and negative binomial models Quiz · 3B.3.1 · 20 questions
- Hypothesis tests for the Poisson distribution Quiz · 3B.4.1 · 20 questions