What term describes planning, directing, and controlling resources to achieve specific project goals?
- Operations scheduling
- Productivity management
- Project management
- Quality assurance
-
Which visual tool uses horizontal bars along a timeline to represent activity durations and overlaps?
- Fishbone diagram
- Gantt chart
- Decision tree
- Critical path diagram
-
What does EST stand for in Critical Path Analysis?
- Estimated total time
- Earliest finish time
- Earliest start time
- Expected standard time
-
What does LFT stand for in Critical Path Analysis?
- Latest finish time
- Lead float time
- Latest start time
- Longest final time
-
How is total float calculated in Critical Path Analysis?
- EST + duration + LFT
- LFT - duration - EST
- EST - duration - LFT
- LFT - EST + duration
-
How is free float calculated for a project activity?
- LFT - duration - EST
- LFT next - duration - EST
- EST next + duration - LFT
- EST next - duration - EST
-
What is the defining characteristic of activities on the critical path?
- Maximum total float
- Zero total float
- Negative free float
- Variable duration
-
In PERT analysis, what does the 'O' symbol represent?
- Overall time
- Optimal finish
- Operational time
- Optimistic time
-
In PERT, what is the formula to calculate expected task time?
- (O + M + P) / 3
- (O + 2M + P) / 4
- (2O + 4M + 2P) / 6
- (O + 4M + P) / 6
-
An activity has O = 2 days, M = 5 days, and P = 14 days. What is its expected time?
- 7 days
- 8 days
- 6 days
- 5 days
-
If two predecessor activities finish at EST 8 and EST 12, what is the EST for the next node?
- 12
- 20
- 8
- 10
-
If two succeeding paths require LFTs of 15 and 18, what is the LFT for the preceding node?
- 16.5
- 15
- 18
- 33
-
Which quantitative project management tool displays task dependencies using network nodes and arrows?
- Pestle analysis
- Gantt chart
- Critical path analysis
- Break-even chart
-
What is the maximum time an activity can be delayed without delaying the start of the next task?
- Pessimistic time
- Free float
- Critical time
- Total float
-
Which of the following is a qualitative factor affecting project management decisions?
- Expected time
- Management style
- Earliest start time
- Total float
-
Why might a business prefer a Gantt chart over Critical Path Analysis?
- Shows resource costs
- Simple visual format
- Calculates floats accurately
- Identifies critical activities
-
An activity has EST of 4, duration of 5, and LFT of 11. What is its total float?
- 3
- 2
- 1
- 0
-
What does the 'P' symbol represent in PERT project management calculations?
- Planned duration
- Project time
- Probable time
- Pessimistic time
-
What does the symbol 'M' represent in PERT project management calculations?
- Minimum completion time
- Mean estimated time
- Most likely time
- Maximum buffer time
-
An activity has EST 6, duration 4, and next activity EST 12. What is its free float?
- 10
- 0
- 2
- 6
Related quizzes
- Enterprise Quiz · 1.1.1 · 20 questions
- Different stakeholder and business objectives Quiz · 2.1.1 · 20 questions
- The market, market size and growth Quiz · 3.1.1 · 20 questions
- Causes and effect of change Quiz · 4.1.1 · 20 questions
- Accounting and finance objectives Quiz · 5.1.1 · 20 questions
- Human resource management objectives Quiz · 6.1.1 · 20 questions
- Marketing objectives Quiz · 7.1.1 · 20 questions
- Business sectors Quiz · 1.2.1 · 20 questions
- Stakeholders Quiz · 2.2.1 · 20 questions
- Demand and supply Quiz · 3.2.1 · 20 questions