Lesson 3D.4.4
3D.4.4 Total float and Gantt charts Quiz: Pearson Edexcel Further Maths, Unit 38
20 questions
In partnership with Revision Ninja
Lesson 3D.4.4, Total float and Gantt charts: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.
Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.
The 20 questions
-
Total float F(i,j) of an activity (i,j) is defined as
- e_j - l_i + duration(i,j)
- e_i - l_j - duration(i,j)
- l_j - e_i - duration(i,j)
- l_j - e_j - duration(i,j)
-
Total float of an activity is
- the time between its start and finish only
- the amount it can be delayed without delaying project completion
- the time its workers spend idle
- the sum of the floats along the whole path
-
A Gantt chart shows
- the workers' pay for each activity
- the net profit of the project
- each activity as a bar on a time axis, with its start and duration
- only the precedence table
-
On a cascade Gantt chart, an activity with total float is drawn
- as a single point at its latest finish
- as a bar starting at its latest start only
- only if it is on the critical path
- as its earliest-start bar, with a line showing the float after it
-
A cascade chart is another name for a
- Venn diagram
- histogram
- precedence table
- Gantt chart
-
The earliest start of activity (i,j) is
- e_j, the earliest time of event j
- l_i, the latest time of event i
- e_i, the earliest time of event i
- l_j, the latest time of event j
-
The latest finish of activity (i,j) is
- e_j, the earliest time of event j
- l_i + duration(i,j)
- l_j, the latest time of event j
- e_i, the earliest time of event i
-
An activity has earliest start e_i = 4, latest finish l_j = 12 and duration 5. What is its total float?
- 5
- 12
- 3
- 8
-
An activity has earliest start e_i = 0, latest finish l_j = 6 and duration 6. What is its total float?
- 12
- 0
- 6
- -6
-
An activity has e_i = 2, l_j = 7 and duration 3. What is its total float?
- 7
- 2
- 4
- -2
-
An activity starts at its earliest time 3, lasts 4 and has total float 2. What is its latest finish?
- 11
- 7
- 5
- 9
-
An activity has total float 5 and lasts 3 days. It is delayed by 4 days. What happens to the project completion?
- No change
- Project delayed by 4
- Project delayed by 9
- Project delayed by 1
-
An activity has earliest start 5, duration 3 and total float 4. What is its latest start?
- 8
- 12
- 7
- 9
-
An activity has e_i = 8, l_i = 10, duration 3, e_j = 11 and l_j = 12. What is its total float?
- 0
- 3
- 1
- 4
-
An activity Y starts at its earliest time 4, lasts 10 and has total float 6. What is its latest finish?
- 16
- 20
- 24
- 14
-
Why can total float be shared between activities on the same path?
- a delay on one float-carrying activity uses up float shared with later activities on that path
- floats are only defined for critical paths
- each activity has private float only
- floats always add up
-
An activity has duration 6, earliest start 2, and its head event has latest time 9. What is its latest start?
- 9
- 2
- 3
- 1
-
Activities A (time 0 to 3), B (time 1 to 5) and C (time 3 to 6) are drawn on a Gantt chart. How many are active at time 2?
- 3
- 1
- 0
- 2
-
Why does delaying a critical activity delay the project, while delaying within its float does not?
- a critical activity has no float, so any delay pushes the finish back, whereas a delay within float only uses slack
- critical activities have longer durations than others
- float is always shared between all activities
- delays only matter when workers are idle
-
An activity has earliest start 3, duration 4 and latest head event time 10. What is its total float, and is it critical?
- 3 units, not critical
- 3 units, critical
- 0 units, critical
- 7 units, not critical
Related quizzes
- Activity networks and precedence tables Quiz · 3D.4.1-3D.4.2 · 20 questions
- Critical path algorithm Quiz · 3D.4.3 · 20 questions
- Resource histograms and scheduling with workers Quiz · 3D.4.5-3D.4.6 · 20 questions
- Proof by mathematical induction Quiz · 1.1 · 20 questions
- Quadratic equations and complex arithmetic Quiz · 2.1-2.2 · 20 questions
- Matrix arithmetic and inverses Quiz · 3.1-3.2 · 20 questions
- Expectation of discrete random variables Quiz · 3B.1.1 · 20 questions
- The Poisson distribution Quiz · 3B.2.1 · 20 questions
- Geometric and negative binomial models Quiz · 3B.3.1 · 20 questions
- Hypothesis tests for the Poisson distribution Quiz · 3B.4.1 · 20 questions