Lesson 3.3.4

3.3.4 Critical path analysis Quiz: Pearson Edexcel Business, Unit 3

20 questions

In partnership with Revision Ninja

Lesson 3.3.4, Critical path analysis: 20 multiple choice questions for the Pearson Edexcel Business (9BS0), Unit 3: Business decisions and strategy, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. What is the main purpose of critical path analysis?

    • Maximum profit calculation
    • Product market share
    • Total labour costs
    • Minimum project duration
  2. What is the critical path in a project network diagram?

    • Shortest duration path
    • Longest sequence path
    • Cheapest activity path
    • Path with float
  3. How much total float do activities on the critical path have?

    • Negative float
    • Maximum float
    • Zero
    • One day
  4. Which calculation pass through a network diagram determines earliest start times?

    • Forward pass
    • Backward pass
    • Critical pass
    • Float pass
  5. Which calculation pass through a network diagram determines latest finish times?

    • Float pass
    • Backward pass
    • Parallel pass
    • Forward pass
  6. What does total float measure in critical path analysis?

    • Minimum activity time
    • Spare time available
    • Total project time
    • Critical delay duration
  7. What major assumption in Critical Path Analysis is often unrealistic in practice?

    • Infinite total float
    • Fixed activity durations
    • Equal path lengths
    • Zero resource costs
  8. In an example network, activity A takes 3 days and is followed by activity C (4 days) and then activity D (1 day). Activity B (2 days) follows A and also leads to D. What is the duration of the critical path?

    • 5 days
    • 10 days
    • 8 days
    • 6 days
  9. In the same network, what is the earliest start time of activity C?

    • 7 days
    • 0 days
    • 3 days
    • 5 days
  10. In the same network, what is the total float of activity B?

    • 0 days
    • 2 days
    • 1 day
    • 4 days
  11. In the same network, which activities form the critical path?

    • B and C only
    • A, C and D
    • A, B and D
    • C and D only
  12. An activity on the critical path is delayed by 2 days. What happens to project completion?

    • 2 days earlier
    • 1 day delay
    • No delay
    • 2 days delay
  13. An activity with 2 days of float is delayed by 1 day. What is the impact on project completion?

    • 1 day earlier
    • 2 days delay
    • 1 day delay
    • No delay
  14. A project has two paths: one of 4, 5 and 2 days (total 11 days) and one of 6 and 3 days (total 9 days). What is the project's minimum duration?

    • 2 days
    • 9 days
    • 11 days
    • 20 days
  15. What is a key benefit of Critical Path Analysis for project managers?

    • Guarantees profit margins
    • Eliminates operational risk
    • Identifies critical activities
    • Prevents staff turnover
  16. Why should a project manager focus resources primarily on critical path activities?

    • Eliminates task dependencies
    • Reduces labour costs
    • Prevents overall delay
    • Increases total float
  17. What is the main risk of using up float on a non-critical activity?

    • Reduces project flexibility
    • Guarantees early finish
    • Shortens project duration
    • Increases total profit
  18. Which limitation occurs when Critical Path Analysis assumes workers can perform multiple tasks simultaneously?

    • Ignores task sequence
    • Ignores resource constraints
    • Overestimates total float
    • Calculates negative float
  19. A project has one path of 5, 3 and 4 days (total 12 days) and another path of 10 and 4 days (total 14 days), both ending in the same final activity. What is the minimum project duration?

    • 9 days
    • 14 days
    • 26 days
    • 12 days
  20. What is the main trade-off when shortening a critical path using overtime?

    • Profit versus revenue
    • Time versus cost
    • Quality versus safety
    • Risk versus output