Lesson 7.05a, Critical path analysis: 20 multiple choice questions for the OCR Further Maths (H245), Unit 4: Discrete Mathematics (Y544), written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. In an activity-on-arc network, what do the nodes represent?

    • Activities
    • Time durations
    • Events
    • Float values
  2. What is a critical path in a directed activity network?

    • Longest path
    • Float path
    • Dummy path
    • Shortest path
  3. What term describes a node where two or more activities meet?

    • Burst event
    • Dummy node
    • Critical node
    • Merge event
  4. What term describes a node where multiple activities begin?

    • Burst event
    • Float event
    • Terminal node
    • Merge event
  5. What pass through an activity network calculates the earliest start times?

    • Float pass
    • Backward pass
    • Critical pass
    • Forward pass
  6. Which process through an activity network determines the latest finish times?

    • Parallel pass
    • Cascade pass
    • Backward pass
    • Forward pass
  7. What is the formula for the total float of an activity?

    • LFT - EST - duration
    • LFT - EST + duration
    • EST - LFT - duration
    • EST + duration - LFT
  8. What does a total float of zero indicate for an activity?

    • It is dummy
    • It is independent
    • It is critical
    • It is delayed
  9. If the critical path duration of a network is 18 days, what is the minimum completion time?

    • 36 days
    • 0 days
    • 9 days
    • 18 days
  10. An activity has a latest finish time of 12 and duration 4. What is its LST?

    • 8
    • 3
    • 48
    • 16
  11. An activity has an earliest start time of 5 and duration 3. What is its EFT?

    • 1
    • 8
    • 2
    • 15
  12. An activity has EST = 4, LFT = 15, and duration = 6. What is its total float?

    • 11
    • 9
    • 25
    • 5
  13. How is the float of non-critical activities typically represented on a cascade chart?

    • Red circles
    • Dashed lines
    • Solid blocks
    • Shaded squares
  14. Two sequential activities A (duration 4) and B (duration 7) form a path. What is total length?

    • 11
    • 28
    • 3
    • 7
  15. If a critical activity is delayed by 2 days, how much is the project delayed?

    • 2 days
    • 4 days
    • 1 day
    • 0 days
  16. An activity has total float 4. If delayed by 3 days, what is the project delay?

    • 3 days
    • 0 days
    • 1 day
    • 7 days
  17. Which float measure assumes predecessor activities finish late and successor activities start early?

    • Independent float
    • Interfering float
    • Free float
    • Total float
  18. What is the difference between total float and free float called?

    • Interfering float
    • Critical float
    • Independent float
    • Dummy float
  19. Why are dummy activities primarily used in an activity-on-arc network?

    • To preserve precedence
    • To increase duration
    • To show float
    • To calculate LFT
  20. On a cascade chart, what can a vertical line across rows help determine at a time?

    • Resource requirements
    • Earliest start time
    • Critical path duration
    • Dummy duration