Lesson DE4-DE6

DE4-DE6 Refining models, Gantt charts and resource levelling Quiz: AQA Further Maths, Unit 5

20 questions

In partnership with Revision Ninja

Lesson DE4-DE6, Refining models, Gantt charts and resource levelling: 20 multiple choice questions for the AQA Further Maths (7367), Unit 5: Optional application 3: discrete mathematics, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. What is a Gantt (cascade) diagram in critical path analysis?

    • A histogram showing the number of resources used in each time period
    • A chart that shows the total float of each activity as a single number
    • A bar chart in which each activity is drawn as a bar from its start time to its finish time against a time axis
    • A network diagram with nodes showing durations and arcs showing precedence only
  2. What is a resource histogram in critical path analysis?

    • A chart showing only the activities on the critical path
    • A chart showing how much of a resource is needed at each point in time, based on a schedule
    • A bar chart of the total duration of each activity
    • A graph of earliest start times plotted against latest start times
  3. What is resource levelling?

    • Adjusting the timing of non-critical activities within their float to reduce peaks in resource use, usually without extending the project
    • Starting every activity at its latest start time
    • Increasing the number of resources until every activity becomes critical
    • Removing all non-critical activities from the project
  4. What is meant by a heuristic procedure, as used in resource levelling?

    • An algorithm that proves the project cannot be completed
    • A method that always gives the exact optimal schedule
    • A rule requiring every activity to be on the critical path
    • A practical method that gives a good schedule quickly, but does not guarantee the optimal schedule
  5. A model of a project assumes unlimited resources, but the real site has only a few workers. Which refinement is most appropriate?

    • Add resource limits to the model, so that activities cannot run together when the workers available would be exceeded
    • Replace every activity duration with the average duration of all activities
    • Ignore the critical path, since the resources are assumed to be unlimited
    • Remove all precedence constraints so that activities can start at once
  6. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. What is the earliest time at which activity E can start in the early start schedule?

    • Time 5
    • Time 9
    • Time 4
    • Time 12
  7. In a Gantt chart with activities drawn from their earliest start times, how is the total float of a non-critical activity usually shown?

    • As a marker placed at the start of the critical path
    • As a separate bar showing its latest start time only
    • As a bar twice as long as its duration
    • As a line or extension after its bar, showing how far it can slip without delaying the project
  8. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. What is the peak number of workers needed at any time in the early start schedule?

    • 6
    • 4
    • 3
    • 5
  9. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. In which time interval does the peak demand of workers occur in the early start schedule?

    • Between time 4 and time 5
    • Between time 0 and time 3
    • Between time 9 and time 12
    • Between time 5 and time 9
  10. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. What is the total number of worker-days needed for the whole project?

    • 12
    • 27
    • 30
    • 24
  11. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. Activity C has float 4. Why might resource levelling move C later within its float?

    • Because moving C reduces the total number of worker-days needed
    • Because moving C within its float can reduce peak demand without delaying the project
    • Because C has zero float and so cannot be moved at all
    • Because C is critical and must be moved to finish earlier
  12. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. If only 3 workers are available at any time, is the early start schedule feasible?

    • No, because the project duration of 12 exceeds the number of workers
    • Yes, because the peak demand is only 3 between time 0 and time 3
    • Yes, because the total of 27 worker-days is below the limit
    • No, because the demand of 4 workers between times 4 and 5 exceeds the limit of 3
  13. If resource levelling delays a critical activity, what is the effect on the project?

    • The critical path changes so that it includes only non-critical activities
    • The project duration is extended, since critical activities have no float
    • The project is unchanged, because levelling moves only non-critical activities
    • The project finishes earlier, since levelling shortens activity durations
  14. When an activity is moved during resource levelling, what must remain true?

    • It must stay within its float, so its predecessors and successors remain satisfied and the project duration is unchanged
    • It must be moved onto the critical path
    • Its float must be exactly equal to its duration
    • It must always start at time zero
  15. Which statement about a Gantt chart showing float is correct?

    • Critical activities are drawn with float lines longer than those of non-critical activities
    • A Gantt chart cannot show critical activities
    • Float lines show the duration of each activity
    • Float lines show how far each non-critical activity can slip, while critical activities show no float
  16. A model assumes that one worker can carry out two activities at the same time. Which refinement is most appropriate?

    • Replace each activity with a single node of zero duration
    • Delete all activities with positive float from the network
    • Add a constraint that each worker can do only one activity at a time, and check the resource histogram against this limit
    • Remove the resource constraint, since the model is already accurate
  17. What is the main purpose of a resource histogram when refining a critical path model?

    • To show whether the schedule needs more resources than are available at any time, so that the schedule can be adjusted
    • To replace the whole network with a single activity
    • To find the critical path directly from the resource numbers
    • To calculate the float of every activity exactly
  18. Activity D needs 2 workers for 5 days. How many worker-days does D require?

    • 5
    • 10
    • 2
    • 7
  19. Two activities that run in parallel each need 3 workers, but only 4 workers are available. Which statement is correct?

    • They can run together, because each needs fewer than four workers
    • They can run together, because their total of six workers is small
    • They cannot run together without exceeding the resources, so one must be delayed within its float or extra workers must be provided
    • They must be run in sequence, which leaves the project duration unchanged
  20. Which statement about heuristic resource levelling is correct?

    • It may not find the best possible schedule, but gives a practical schedule that respects precedence and resource limits
    • It guarantees the smallest total float across the network
    • It always finds the minimum possible project duration
    • It requires that every activity be on the critical path

All AQA Further Maths quizzes