Lesson 3.10.3

3.10.3 Managing strategic implementation Quiz: AQA Business, Unit 10

20 questions

In partnership with Revision Ninja

Lesson 3.10.3, Managing strategic implementation: 20 multiple choice questions for the AQA Business (7132), Unit 10: Managing strategic change, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. Why does leadership matter in implementing strategy?

    • Leaders should avoid communicating with staff during implementation, so that the strategy is not diluted
    • Leaders set direction, motivate staff and secure commitment, which helps translate strategy into action
    • Leadership is irrelevant to implementation, because strategy executes itself once it has been written down
    • Leaders are needed only to sign documents, so their involvement in the day-to-day implementation has little value
  2. Why is communication important in strategic implementation?

    • It is only needed at the start of a strategy, and once implementation begins no further communication is required
    • It replaces the need for leadership, because a clear memo can carry out all the tasks of implementation
    • It should be limited to senior managers, so that front-line staff do not receive any information that could confuse them
    • It helps staff understand the strategy and their role in it, which increases commitment and reduces confusion
  3. Why does organisational structure matter in strategic implementation?

    • Structure only matters to the human resources department, and it does not affect the business's operations or strategy
    • Structure should be left unchanged in every case, so that staff are not confused by any adjustment to reporting lines
    • Structure has no effect on strategy because all strategies succeed regardless of how the business is organised
    • A structure that supports the strategy helps allocate responsibilities and resources to the activities that deliver it
  4. What is network analysis used for in strategic implementation?

    • Mapping the physical computer network of a business to identify the location of each server in the building
    • Recording the social networks of employees in order to measure how often they meet each other for lunch
    • Planning and scheduling interdependent activities, showing the sequence and timing needed to complete a project
    • Measuring the number of customers who connect with a business through social media platforms each week
  5. In network analysis, what is the critical path?

    • The set of activities that can be started at any time without any reference to other activities in the network
    • The shortest route through the network that avoids all activities that are dependent on earlier ones
    • The sequence of activities that carries the lowest cost for the project as a whole across all tasks
    • The longest sequence of dependent activities through the network, which sets the minimum time to complete the project
  6. What is total float in network analysis?

    • The number of activities that can be carried out at the same time by different teams in the business
    • The time taken for the project to start after the planning stage has been finished by the managers
    • The amount of time an activity can be delayed without delaying the completion of the whole project
    • The total cost of all activities in the network, which is added together to find the budget for the project
  7. In a network, activity A takes 3 days and has no predecessor. Activity B takes 2 days and follows A. Activity C takes 4 days and follows A. Activity D takes 1 day and follows both B and C. What is the duration of the critical path?

    • 6 days
    • 5 days
    • 8 days
    • 10 days
  8. Using the network in which A takes 3 days, B takes 2 days after A, C takes 4 days after A, and D takes 1 day after B and C, what is the total float of activity B?

    • 4 days
    • 0 days
    • 2 days
    • 1 day
  9. Which activities lie on the critical path in the network where A takes 3 days, B takes 2 days after A, C takes 4 days after A, and D takes 1 day after B and C?

    • A, B and D
    • B, C and D
    • A, B and C
    • A, C and D
  10. A network analysis shows an activity with zero total float. What does this imply?

    • The activity is not needed for the project and can be removed from the plan without any consequence
    • The activity can be delayed by any amount without affecting the project completion date at all
    • The activity has no cost associated with it, so it does not affect the project budget in any way
    • Any delay to that activity will delay the whole project completion date
  11. Why might a project manager amend a network diagram during implementation?

    • The network diagram never needs changing once it has been drawn, because all projects run exactly to the original plan
    • Events such as delays or new information change the activities, durations or dependencies, so the plan must be updated
    • Amendments are only needed when the project is complete, so that managers can record what actually happened
    • Amending the diagram is illegal under company law unless the chief executive has approved every single change
  12. Which of the following best describes the interpretation of a network diagram?

    • Measuring the profit earned by each activity within the project, which is recorded on the diagram
    • Counting the number of employees who are involved in each activity without considering the order of tasks
    • Identifying the earliest and latest start times, the critical path and the float available for each activity
    • Recording the colour of the activity boxes to show which staff member is responsible for each one
  13. Why must a manager pay attention to the critical path during implementation?

    • Because activities on the critical path can be ignored once they have started, since they cannot slip
    • Because delays on the critical path directly push back the completion of the entire project
    • Because the critical path is only relevant to the accounts team, who need it for the financial reporting
    • Because activities on the critical path are always cheaper than other activities in the project plan
  14. What is a common reason strategies fail during implementation?

    • An excess of staff being involved in the planning, which makes the strategy too complicated to deliver
    • A decision to implement the strategy only when the business is operating at its maximum capacity each month
    • Poor communication and insufficient commitment from those who must carry the strategy out
    • Too much attention being paid to communication with staff, which makes the strategy too well understood
  15. Evaluate the value of network analysis for managing a project's implementation.

    • It shows dependencies and critical activities clearly, but it relies on accurate estimates and must be updated as conditions change
    • It guarantees that the project will finish on time, because the diagram removes all uncertainty about durations
    • It replaces the need for any communication with staff, because the diagram tells everyone what to do
    • It is only useful for building projects, so managers in service businesses have no reason to use it at all
  16. Evaluate the role of leadership in implementing a difficult strategic change.

    • Leadership has no role in difficult change, because the strategy will implement itself once the plan is approved by the board
    • Leadership should be avoided during difficult change, because staff prefer to make their own decisions without direction
    • Leadership builds trust and commitment, but its effect depends on consistent communication and alignment with structure and culture
    • Leadership is always sufficient on its own, so structure, communication and culture have no further role to play
  17. A firm reorganises its departments to support a new strategy but staff remain unclear about their roles. What is the most likely problem?

    • The strategy has been fully implemented, so unclear roles are simply a sign of successful change in the firm
    • The problem is caused by excessive communication, which has confused staff about the purpose of the reorganisation
    • The structure has been changed without adequate communication, so responsibilities are not understood and implementation suffers
    • The structure has been changed perfectly, so there is no problem and the implementation should be fully complete
  18. Which factor is most important when a business implements a strategy that requires a new cross-functional team?

    • Allowing each department to set its own strategy, which will then be combined later without any co-ordination
    • Clear accountabilities and co-ordination between departments, supported by leadership
    • Avoiding any formal structure so that the team can change its goals each week as it sees fit
    • Keeping each department completely separate so that they do not need to co-operate on any task
  19. A project has a planned completion of 20 days, but an activity on the critical path is delayed by 3 days. What is the effect on the project?

    • The project completion is delayed by 3 days unless recovery action is taken
    • The project completion is extended by 20 days, which is the full planned duration of the project
    • The project finishes early by 3 days because delays on the critical path always save time overall
    • The project completion is unaffected because the delay occurs on an activity that is not critical in any way
  20. Which action would best reduce the risk of delay on a critical path in network analysis?

    • Removing all dependencies from the network so that activities can be carried out in any order at any time
    • Delaying the start of the critical activities until all other tasks in the project have been completed
    • Ignoring the critical path and concentrating resources on activities that have large float instead
    • Adding resources or re-sequencing work to shorten critical activities, while monitoring progress closely